Thank you Mr. Tay!! U are so resourceful
So along ave 10 & ave 1 will be integrated green with the first floor landscaping. They haven't touched ave 10 side yet, another 2 mths to complete?
Also, need to lay decking for swimming pools, club house, and long viewing gallery from BBQ pits to ave 10, even concurrently doing, also another 2 mths?
Street lamp installed, baby pool lighting under the seating on already n realy nice
tall trees all planted, they are busy for the grass, flowers n bushes now.
Driveway is quite straightforward I think? The BBQ huge roof only one day job? Flooring for tennis court n basketball court not started...
What else they haven't started? Maybe we cross check with the site map to avoid any surprise
Will there be some underneath lighting between baby pool & adult pool? I can't tell if its installed...